About Service
A service that allows the customer to intake testing water and perform a leak test A method in which pipelines, boilers, and fuel tanks are tested for strength and potential for leakage. This system helps maintain safety standards for equipment over time. These permits are issued within a certain period of time in the environmental permit.
Steps
The client submits the required documents.
The site is inspected.
The data has been checked
Issuance of permit
Required Documents
- An official letter to carry out the operation
environmental permit for the project.
Environmental License for establish a project if new project.
A copy of the valid contract between the main contractor and the project owner.
Analysis of sea water sample only.
Material safety data sheet for the chemicals used, if any.
Material safety data sheet for the chemicals used, if any.
If fresh water is used, a water quality certificate from the supplier shall be attached.
A detailed plan showing the starting point and sequence of tanks to the point of unloading, approved by the Planning Department in Fujairah Municipality or Fujairah Port, depending on the location.
Waste management plan for waste if hydrotest from maintenance of existing project)
Terms of Service
All contractor licensed in Fujairah.
Project has (Environmental license if project exist)
Environmental License for establish a project if new project.
Fees
Fees Catagory | Amount |
---|---|
sea water intake | 5000 |
Discharge of seepage test water into the sea (per 50,000 m3) | 10000 |
Drainage of fresh water leakage test on land (per 50,000 m3) | 3000 |
Time
2 working days |
---|