About Service
Approval of the technical summary, which contains all the technical data of the project such as equipment, process flow, raw materials used, as well as the proposed environmental baseline surveys at the project site and neighboring areas, which is one of the basic requirements for obtaining initial approval for all categories of projects.
Steps
The client submits all the technical data of the project to the customer service counter Fujairah Environment Authority through an approved environmental consultancy company
The transaction is forwarded to the concerned department to review the submitted data and issue technical decision.
Required Documents
EIA ToR/ SoW
FEA Initial Environmental NOC
Valid land map for the proposed site
Site layout
Valid contractor trade license
Terms of Service
the project has a significant or medium impact on the environment, i.e. within the yellow or red categories according to the approved classification of Fujairah Environment Authority and according to the provisions of Federal Law No. 24 of 1999 and its amendments regarding the protection and development of the environment
Fees
Fees Catagory | Amount |
---|---|
N/A | 0 |
Time
10-14 days |
---|